Who: Techo for Eastpack Coolstore
Products: 5000L Insulated Tanks
Where: Te Puke
Why: Glycol Storage


The cool store had an existing freon cooling system and the brief was to upgrade it to a package Ammonia Chilling plant with glycol water tank, primary pump and three secondary loops supplying banks of evaporators. Techo was engaged by Raeco Servcies to do the process design, make up pump skids and install tank, pumps, pipework and all equipment.
Promax was pleased to assist Techo with the tight timeline, with an order being issued about 3 weeks before kiwifruit were to be stored.